OCHIL – OGILVIE, EDINBURGH
Duration of build 5 weeks – Sept – Oct 2016
Fifth floor & roof construction of five storey student accommodation – area 1800m2
All components were manufactured off-site to reduce construction time on site, limiting craneage to 7 days and negating the need for an internal fall arrest system during on site construction.
Off-site construction & on-site erection.
All craneage services, 5th floor.